Niš BESS Facility
Standalone grid-scale storage positioned for balancing and ancillary services in southern Serbia, contracted around emerging capacity and reserve markets.
Capacity
60 MWh
Development stage
Permitting
Location
Niš, Serbia
Timeline
Construction Q2 2027 — COD Q1 2028
Total capex
EUR 31m
Turnkey EPC
Revenue stack
3 streams
Balancing, arbitrage, capacity
Target equity IRR
14.1%
Merchant-weighted
Availability
97%
Guaranteed under O&M
Investment opportunity — Strategic equity · EUR 31m
Schedule an investment meetingProject gallery
Drone photography & site views




Technical specifications
Engineered to bankable standards
Energy capacity
60 MWh
Power rating
30 MW
Chemistry
LFP, liquid cooled
Round-trip efficiency
88%
Cycles
1.5 / day
Grid connection
35 kV
Serbia
Niš, Serbia
Construction timeline
Project lifecycle
2025
Site and connection secured
2026
Permitting submitted
2027
Construction
2028
Commercial operation