Belgrade Warehouse Solar
A distribution-centre rooftop delivered without interrupting logistics operations, cutting the tenant's grid demand charge across peak hours.
Capacity
3.1 MWp
Development stage
Operational
Location
Belgrade, Serbia
Timeline
Delivered in 7 months — COD 2025
Tenant saving
31%
Blended cost per kWh
Payback
5.4 years
Post-incentive
Availability
99.2%
Since energisation
O&M
20 years
Full-scope contract
Investment opportunity — Operating asset · yield co-investment
Schedule an investment meetingProject gallery
Drone photography & site views




Technical specifications
Engineered to bankable standards
Installed capacity
3.1 MWp
Annual yield
3.9 GWh
Self-consumption
82%
Roof area
19,400 m²
Structure
Ballasted, non-penetrating
CO₂ avoided
2,200 t / year
Serbia
Belgrade, Serbia
Downloads
Construction timeline
Project lifecycle
2024
Energy audit & design
2024
Permits and financing
2025
Construction
2025
Commercial operation