Haifa Industrial Park — Industrial project in Israel
All projects
IsraelIndustrialCompleted

Haifa Industrial Park

Multi-roof industrial deployment across a manufacturing park, engineered around continuous production and heavy on-site load.

Capacity

6.8 MWp

Development stage

Operational

Location

Haifa, Israel

Timeline

Delivered in 11 months — COD 2026

Energy cost cut

28%

Site blended tariff

Payback

4.9 years

Achieved

Downtime

0 hours

Production impact

O&M

20 years

Guaranteed availability

Investment opportunity — Operating asset · portfolio aggregation

Schedule an investment meeting

Project gallery

Drone photography & site views

Manufacturing complex from the air
Manufacturing complex from the air
Rooftop array coverage
Rooftop array coverage
Inverter room
Inverter room
Module detail
Module detail

Technical specifications

Engineered to bankable standards

Installed capacity

6.8 MWp

Annual yield

10.2 GWh

Roofs

7 buildings

Self-consumption

91%

Monitoring

String-level, real time

CO₂ avoided

5,800 t / year

Israel

Haifa, Israel

Grid connection · Secured

Construction timeline

Project lifecycle

  1. 2024

    Feasibility & load modelling

  2. 2025

    Construction across 7 roofs

  3. 2026

    Full energisation